Combined formula for Time and Work

Another important concept that is used in time work problems is the combined efficiency of

two or more persons. In questions on time and work, the rates at which certain persons or

machines work alone are usually given, and it is necessary to compute the rate at which they

work together (or vice versa).

Let us say, for example, it takes 3 & 6 hours for Bahubali and Kattappa, respectively, to

break a dam working alone. So, in 1 hour Bahubali would have broken one-third or 1/3rd or

33% of the dam and Kattappa would have broken one-sixth or 1/6th or 16.67% of the dam.

In 2 hours, Bahubali would have destroyed 1/3*2 or 33% *2 = 66.66% of the dam and

kattappa would have destroyed 1/6th *2= 1/3= 33.33% of the dam. So if Both Bahubali and

Kattappa work together, they would have destroyed 66.66+ 33.33 (2/3+1/3) or 100% of the

dam in 2 hours. Therefore, if both worked together for 1 hour, they would have destroyed 1/3

+ 1/6= ½ or half of the dam. Thus in 2 hours, the dam is destroyed.

Generalizing, we conclude that in 1 hour, Bahubali does 1/r of the job, Kattappa does 1/s of

the job, and Bahubali & Kattappa together do 1/h of the job or that together they can finish

the job in ‘h’ hours where the formula for work comes out as 1/r + 1/s = 1/h.

Try to solve the following time and work questions using time and work formula:

Q.1.In the beginning, Ram works at a rate such that he can finish a piece of work in

24 hrs, but he only works at this rate for 16 hrs. After that, he works at a rate such

that he can do the whole work in 18 hrs. If Ram is to finish this work at a stretch, how

many hours will he take to finish this work?

a) 12 hrs

b) 18 hrs

c) 11½ hrs

d) 15 hrs

e) 22 hrs

Comments

  1. Explanation:Ram’s 16 hr work = 16/24 = 2/3. Remaining work = 1 – 2/3 = 1/3.
    Using work and time formula: This will be completed in 1/3 × 18 i.e. 6 hrs.
    So, total time taken to complete work = 16 + 6= 22 hrs.

    ReplyDelete
  2. Given : Ram works at a rate such he will end a chunk of labor in twenty-four hours, however, he solely works at this rate for sixteen hrs.

    After that, he's employed at a rate such he will do the complete add eighteen hrs.

    According to the question,
    Ram’s sixteen time unit work = 16/24 = 2/3.
    Remaining work = one – 2/3 = 1/3.

    Using work and time formula:
    This will be completed in 1/3 × eighteen i.e. 6 hrs.
    So, the total time is taken to finish work = 16 + 6
    = 22 hours.

    ReplyDelete
  3. e) 22 hours
    Work done in beginning = 16/24 = 2/3
    Total work =1
    Remaining work= 1 - 2/3 = 1/3
    Applying work time formula= 1/3 *18 = 6 hours
    Total time to complete work = 16+6 = 22 hours

    ReplyDelete
  4. Work done in beginning =16/24 = 2/3
    Total work = 1
    Remaining work= 1-2/3 = 3-2/3 =1/3
    Using time formula 1/3*18 = 6
    Total time needed= 16+6= 22
    E) 22

    ReplyDelete
  5. Ans- e) 22hrs
    Total Work- 1
    Work done in the beginning- 16/24= 2/3
    Remaining Work- 1-2/3= 3-2/3=1/3
    1/3*18 =6 hours ----------( Work time formula)
    Therefore total time needed to complete work => 16+6 = 22 hours

    ReplyDelete
  6. Ans- e) 22hrs
    Work done in the beginning→ 16/24= 2/3
    Total Work→ 1
    Remaining Work →1-2/3
    → 3-2/3
    → 1/3
    By using the work time formula, the work will be completed in:
    1/3*18 =6 hours
    Therefore total time needed to complete work→16+6 = 22 hours

    Sanjam Bedi
    10-B

    ReplyDelete
  7. Work done by Ram in the beginning = 16/24 = 2/3
    Total Work = 1
    Remaining Work = 1- 2/3 = 1/3
    By using the time and work formula , the time taken to complete remaining work= 1/3 * 18 hr = 6hr

    Therefore, Total time taken to complete work = 16 hr + 6 hr = 22 hr.
    Hence, option (e) 22 hrs is the answer.

    -By Somil Kashyap

    ReplyDelete
  8. Well done children.

    ReplyDelete

Post a Comment

Popular posts from this blog

A fire in a building B...

For going to a city B ...